Current Projects


Maseru peri- urban phase 2 water project Completed and handed over to the Client on the 30th June, 2011

 

  Maseru Peri-urban Phase II Water Project


Project implementation status
Reticulation: 302 Kilometers of pipelines of varying diameters 25 mm to 315 mm laid in the areas mentioned above representing 100% of the coverage

Reservoirs: All the reservoirs are 100% complete (High North Reservoir, and Thetsane steel tank)

Pumping Stations: Both medium north pumping station and south west booster pumping station civil works and electromechanical works are 100% complete.

Project Duration

The project was awarded to UNIK Construction Engineering for works and Consulting Engineering Centre for consulting services in December 2007 with the expected duration of 24 months followed by 12 months Defects Liability Period.

Funding Agency
The project was funded by the Arab Bank for Economic Development of Africa (BADEA), OPEC, and the Government of Lesotho.
 

  Three towns water and sanitation project - Completed and handed over to the Client on the 30th March, 2011


Project implementation status
Reticulation: 100% COMPLETE in all the 3 Towns.

Rising mains:
100% COMPLETE

Reservoirs:
All the reservoirs in the 3 Towns are 100% complete.

Steel tanks:
100% COMPLETE in the 3 Towns

Drilling Programme:
100% complete.

Sewerage networks:
100% COMPLETE in all the 3 Towns.

Rehabilitation of old WWTP: Rehabilitation works of old WWTP in Roma and TY are complete. Security fence, toilets and tool rooms are also complete. Disludging at Maputsoe WWTP is complete and the security fence, toilet and tools` room are also complete.

New wastewater treatment plant @ Roma: 100% COMPLETE

Project Duration
The revised completion date of this project was 30th March, 2011.

Funding Agency
The project was financed by the European Commission under European Development Fund (EDF9)

 

  Tikoe Thetsane Industrial estates water supply project - Completed on the 30th June, 2011


Project implementation status
Pipelines: 100% COMPLETE

10 Mega liters Reservoir: 100% complete

20 ML Treatment plant: Civil works and electromechanical works are 100% complete.

River intake works: 100% COMPLETE

Project Duration
The revised completion date of this project was 30th June, 2011 followed by 12 months defects liability period.

Funding Agency
The project is fully funded by Government of Lesotho under the industrialization programme of the ministry of Trade, Industry, Cooperatives and Marketing.


 

  Urban and peri urban water supply


Project scope
This project is funded by Millenium Challenge Corporation (MCC). The scope of works involves the rehabilitation, upgrading, extension and new works in the following components of a water system:

bullet

Water sources,

Water treatment works,

Reservoirs,

Bulk pipelines,

Distribution pipelines, and

House connections


The project comprises of four packages, which are:

  1. Package 1, which includes Maseru and Mazenod,

  2. Package 2 is Semonkong,

  3. Package 3 includes Mafeteng, Mohale`s Hoek, Quthing, and Qacha`s Nek,

  4. Package 4 includes Mokhotlong, Butha-Buthe, and Leribe

  5. Package 5 is Mapoteng

Project implementation status
Package 1: ENTSHA HENRA JV of South Africa has been awarded the contract for Construction of this package. The commencement date of the contract is 27th May, 2011 and the expected completion date is the 2nd September, 2012. The Contractor has started by exposing the existing services along the routes of the pipelines. Actual construction work is estimated to start on the 9th August, 2011.

Package 2: The consultant is working on the final design report. Construction is planned to start in December, 2011, and end in September, 2012.

Package 3: The consultant is working on the comments made on the final design report. Construction is planned to start in December, 2011, and end in November, 2012.

Package 4: The construction contract has been awarded in July, 2011. Negotiations with the prospective contractor are in progress. Construction is planned to start by end of August, 2011, and end in July, 2012.

Package 5: The final design report is under preparation. Construction is planned to start in November, 2012, and end in August, 2013.
 

 